Question

Return to RFP page

Question

How is the Contractor to be compensated if the City requests a read be completed outside of the regular schedule (ref” read meter at a later date if necessary”)?

Answer

Compensation for meter reads requested by the City outside of the regular schedule will be negotiated in the contract. Currently City staff take care of special reads.