Question

Based on the details provided here, it is our understanding that the Contractor is to be responsible for the provision of the manual meter reading system for the purposes of this contract. Please confirm if our understanding is correct, or if incorrect, please provide additional supporting details.

Answer

Yes, the Contractor is to be responsible for the provision of the manual meter reading system for the purposes of this contract.